SH 3503-2007 石油化工建設工程項目交工技術文件規(guī)定 中英文對照表格.rar
SH 3503-2007 石油化工建設工程項目交工技術文件規(guī)定 中英文對照表格.rar,SH,3503-2007,石油化工建設工程項目交工技術文件規(guī)定,中英文對照表格,3503,2007,石油化工,建設,工程項目,交工,技術,文件,規(guī)定,中英文,對照,表格
SH 3503–J617
DCS機柜、儀表盤、
操作臺安裝檢查記錄
Installation Inspection Record of DCS Cabinets, Instrument Panels and Operation Consoles
工程名稱:
Project Description:
單元名稱:
Unit Description:
名稱Name
型號Type
位號Tag No
檢 查 項 目
Item of Inspection
檢查結果
Result of Inspection
檢查日期
Inspection Date
備 注
Remark
1
外觀無破損、無變形,內外表面無油漆脫落、無受潮、銹蝕等缺陷
No visual damage or deformsand no paint ripoff, no humidity and rusting on inner and outer surface.
2
基礎型鋼平直、牢靠,外形尺寸與機柜、儀表盤、操作臺的尺寸一致,表層除銹防腐
Foundation H steel is flat and firm, visual size is in accordance with that of cabinets, instrument panel and operation consoles, and surface is rust-proofing erosion-proofing.
3
機柜、盤、臺的安裝布置、銘牌、型號、位號、數(shù)量、外形尺寸、儀表開孔尺寸符合設計要求
Installation and position of cabinets, panel and consoles, label, type, tag number, quantity, dimension and hole size of instrument are in conformity with the design.
4
儀表、DCS內部組件的型號、規(guī)格、數(shù)量、安裝位置符合設計要求,無破損、松動、脫落
Type, specification, quantity and installation site of instruments and interior components in DCS are in conformity with the design, and no damage, looseness or falling apart exists.
5
DCS機柜、儀表盤、操作臺的垂直度、水平度、盤間接縫間隙、頂部高差、正面平面度符合規(guī)范要求,與基礎型鋼之間采用防銹螺栓牢固連接
Verticality, levelness, clearance between panels, height difference on top and front flatness of DCS container, instrument panel and operation desk are in conformity with the design, and foundation structural steel is fixed by rust-proofing bolt.
6
盤間電纜(含專用電纜)的型號、規(guī)格、數(shù)量,電纜頭、標志牌制做及接線(含內部接線)正確、牢靠、整齊、美觀、齊全,符合設計、規(guī)范要求
Type, specification and quantity, connector and typeof cable (including special cable), and wire connection (including inner wire) are correct, firm, orderly, good-looking, complete, and are in conformity with design and regulation.
7
機柜、儀表盤、操作臺及室內地板下、電纜溝內無塵埃、異物,電纜出、入口應封閉
No dust or foreign object exists in machine container, instrument panel, operation desk, underground and cable ditch, and the entrance and exit of cable should be sealed.
8
電纜(線)的導通、絕緣電阻符合規(guī)范要求
Conductivity and insulation resistence of cable or wire are in conformity with standards.
9
就地儀表盤安裝在光線充足,環(huán)境干燥、操作維修方便的地方,且有良好的密封性
Local instrument panel is installed in place with abundant light, dry environment, convenient for operation and maintenance, and with excellent sealing.
10
電源系統(tǒng)符合設計、規(guī)范要求
Power system is in conformity with requirements of design and standard.
11
工作接地系統(tǒng)符合設計、規(guī)范要求
Earthing system is in conformity with requirements of design and standard.
12
保護接地系統(tǒng)符合設計、規(guī)范要求
Protection earthing system is in conformity with requirements of design and standard.
13
屏蔽接地系統(tǒng)符合設計、規(guī)范要求
Shielding earthing system is in conformity with requirements of design and standard.
14
隨盤技術文件應齊全Technical documents together with instrument are complete.
備注:
Remark:
建 設 / 監(jiān) 理 單 位Owner/Supervision Unit
施 工 單 位Construction Unit
專業(yè)工程師:Discipline Engineer:
年(Y) 月(M) 日(D)
技術負責人:Technical Responsible Person
質量檢查員:Quality Inspector
檢 測 人:Tester
年(Y) 月(M) 日(D)
收藏